问题详情

答题翼 > 问答 > 计算机类考试 > 正文
目录: 标题| 题干| 答案| 搜索| 相关

● The project (73)is a key input to quality planning since it documents major project deli


● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis

请帮忙给出正确答案和分析,谢谢!

参考答案
您可能感兴趣的试题