● (73) is a method used in Critical Path Methodology for constructing a project schedule n


● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between

them.

(73)

A.PERT

B.AOA

C.WBS

D.PDM

请帮忙给出正确答案和分析,谢谢!

参考答案