● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are f


● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.

(75)

A.Finish-to-Start

B.Finish-to-Finish

C.Start-to-Start

D.Start-to-Finish

请帮忙给出正确答案和分析,谢谢!