● (73) is a method used in Critical Path Methodology for constructing a project schedule n


● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between

them.

(73)

A.PERT

B.AOA

C.WBS

D.PDM

参考答案