● Project Time Management includes the processes required to manage timely completion of t


● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

(74)

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities