● Project schedule management is made up of six management processes including: activity d


● Project schedule management is made up of six management processes including: activity definition, activity sequencing, (71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating