There are over 30 stakeholders on your project . The project is being done in another coun


There are over 30 stakeholders on your project . The project is being done in another country with people from three countries as team members . Which of the following is the MOST important thing to keep in mind?

A.The communication channels will be narrow.

B.Many competing needs and objectives must be satisfied .

C.There must be one sponsor from each country .

D.Conflicts of interest must be disclosed .

请帮忙给出正确答案和分析,谢谢!

参考答案