● A project manager believes that modifying the scope of the project may provide added val


● A project manager believes that modifying the scope of the project may provide added value service for the customer .The project manager should()()A. assign change tasks to project membersB. call a meeting of the configuration control boardC. change the scope baselineD. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline